Project schedule

Construction started April 8, 2013, and is expected to be complete in early 2014. Below is the current schedule of work, as well as other anticipated major milestones.

Construction updates

April 7 - April 20

Over the next two weeks, crews are expected to continue the following general activities:

  • Install stop light upgrades and traffic detection loops at the intersection of 67th Avenue NE and 204th Street NE
  • Continue installing Centennial Trail lights and street lights at various locations between 204th Street NE and Lebanon Street
  • Roadway grading on the east side of 67th Avenue NE at the intersections of 204th Street NE, 211th Place NE, and Lebanon Street
  • Fence installation along the Centennial Trail between 204th Street NE and the Pioneer Museum
  • Continue miscellaneous roadside cleanup, landscaping and property restoration
  • Begin early project wrap-up work

March 24 – April 6

Over the next two weeks, crews are expected to continue the following general activities:

  • Install stop light upgrades at the intersection of 67th Avenue NE and 204th Street NE
  • Install Centennial Trail lights and street lights at various locations between 204th Street NE and Lebanon Street
  • Prepare, grade, and pave portions of Centennial Trail, pending favorable weather
  • Prepare and pave curbs at various locations on the east side of 67th Avenue NE between 204th Street NE and Lebanon Street, pending favorable weather
  • Plant vegetation and seed grass to the east side of 67th Avenue NE, adjacent to Centennial Trail
  • Conduct miscellaneous roadside cleanup, landscaping and property restoration

Major schedule milestones

  • July 19-22 – Portage Creek Culvert installed, required full roadway closure
  • August 2-5 – Prairie Creek Culvert installed, required full roadway closure
  • Early 2014 – Roadway construction and Centennial Trail complete

Completed work

Prior to construction, crews relocated utilities along the 67th Avenue corridor. In preparation of this work, the city moved several artifacts, including a 700 year-old tree stump that was located in front of the Stillaguamish Valley Pioneer Museum. A video of the crew moving the stump can be found on the Photos/Video page.

It has taken many seasons of hard work to get to this point in the project and we look forward to the end result!

March 17 – March 23

Crews were scheduled to:

  • Install fiber optic conduit in and adjacent to Lebanon Street between 67th Avenue NE and S Olympic Avenue
  • Install fiber optic conduit on the west side of 67th Avenue NE adjacent to 204th Street NE
  • Conduct miscellaneous roadside cleanup, landscaping and property restoration

February 17 – March 16

Crews were scheduled to:

  • Install Centennial Trail light foundations and street light foundations at various locations between 204th Street NE and Lebanon Street
  • Prepare, grade and pave driveway approaches on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE, pending favorable weather
  • Install utility conduit adjacent to Lebanon Street between 67th Avenue NE and S Olympic Avenue
  • Conduct miscellaneous roadside cleanup, landscaping and property restoration

January 27 – February 16

Crews were scheduled to:

  • Install Centennial Trail light foundations and street light foundation at various locations between 204th Street NE and Lebanon Street
  • Grade Centennial Trail on the eastside of 67th Avenue NE between 211th Place NE and Lebanon Street
  • Pave the east side of 67th Avenue NE between 204th Street NE and 211th Place NE, pending favorable weather
  • Prepare and pave sidewalks on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE
  • Install utility conduit adjacent to Lebanon Street between 67th Avenue NE and S Olympic Avenue

Week of January 20

Crews were scheduled to:

  • Continue installing Centennial Trail light foundations at various locations between 204th Street NE and 211th Place NE
  • Finish excavation on the eastside of 67th Avenue NE between 211th Place NE and Lebanon Street
  • Finish roadway grading and start paving on the east side of 67th Avenue NE between 204th Street NE and Lebanon Street, pending favorable weather
  • Continue preparations for placement of sidewalks on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE
  • Continue miscellaneous roadside cleanup, landscaping and property restoration

Week of January 13

Crews were scheduled to:

  • Continue installing Centennial Trail light foundations at various locations between 204th Street NE and 211th Place NE
  • Finish excavation on the eastside of 67th Avenue NE between 211th Place NE and Lebanon Street
  • Finish roadway grading ahead of paving on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE, pending favorable weather
  • Begin preparations for placement of sidewalks on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE
  • Continue miscellaneous roadside cleanup, landscaping and property restoration

Week of January 6

Crews were scheduled to:

  • Resume installing curb and gutter on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE
  • Resume installing lights and signals at various locations on 67th Avenue NE between 204th Street NE and 211th Place NE
  • Begin paving on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE, pending favorable weather
  • Continue miscellaneous roadside cleanup, landscaping and property restoration

Week of December 16

Crews were scheduled to:

  • Conduct night work on the evenings of Monday, December 16, through Thursday, December 19, from 7 p.m. to 7 a.m. at the intersection of 67th Avenue NE and 204th Street NE. Crews will be continuing to install sanitary sewer and non-potable water lines through the intersection.
  • Prepare for curb and gutter installation on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE
  • Continue excavation to prepare for paving on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE
  • Continue to install lighting for the Centennial Trail between 204th Street NE and 211th Place NE
  • Continue miscellaneous roadside cleanup, landscaping and property restoration

Week of December 9

Crews were scheduled to:

  • Conduct utility work in the intersection of 67th Avenue NE and 204th Street NE on Monday, December 9, through Wednesday, December 11
  • Begin placing curb and gutter on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE
  • Continue excavation to prepare for paving on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE
  • Continue installing lights and signals at various locations on 67th Avenue NE and 204th Street NE
  • Continue miscellaneous roadside cleanup, landscaping and property restoration

Week of December 2

Crews were scheduled to:

  • No work is expected over the Thanksgiving holiday weekend (Thursday, November 28, through Sunday, December 1)
  • Complete backfilling and grading above the block wall on the west side of 67th Avenue NE
  • Prepare and pave the sidewalk on the east side of 67th Avenue NE near the 204th Street intersection
  • Begin excavation and prepare for paving on the east side of 67th Avenue NE between 204th Street NE and 211th Place NE
  • Begin installing conduit for street lights at various locations on 67th Avenue NE and 204th Street NE
  • Continue miscellaneous roadside cleanup, landscaping and property restoration

Week of November 25

Crews were scheduled to:

  • Complete backfilling and grading above the block wall on the west side of 67th Avenue NE between the museum and Twin City Foods
  • Continue miscellaneous roadside cleanup, landscaping and property restoration
  • No work is expected over the Thanksgiving holiday weekend (Thursday, November 28, through Sunday, December 1)

Week of November 18

Crews were scheduled to:

  • Begin placing curb and gutter on the east side of 67th Avenue between the museum and 204th Street NE
  • Continue constructing a block wall on the west side of 67th Avenue NE between the museum and 204th Street NE
  • Continue installing the 24-inch sanitary sewer line on the east side of 67th Avenue NE between the museum and 204th Street NE
  • Complete installation of stormwater crossings between the museum and the intersection of 204th Street NE on the east side of 67th Avenue NE
  • Continue miscellaneous roadside cleanup, landscaping and property restoration

Week of November 11

Crews were scheduled to:

  • Conduct night work on Thursday, November 14, from 7 a.m. to 7 p.m., at the intersection of 67th Avenue NE and 204th Street NE. Crews will be sawcutting the pavement in preparation for installing sanitary sewer and non-potable water lines through the intersection the following week.
  • Begin placing curb and gutter on the east side of 67th Avenue between the museum and 204th Street NE
  • Continue constructing a block wall on the east side of 67th Avenue NE between the museum and 204th Street NE
  • Continue installing lights and signals on Centennial Trail near the Prairie Creek culvert at 69th Avenue
  • Continue installing the 24-inch sanitary sewer line on the east side of 67th Avenue NE between the museum and 204th Street NE
  • Prepare and pave the sidewalk on the east side of 67th Avenue NE near the Prairie Creek culvert at 69th Avenue
  • Complete installation of stormwater crossings between the museum and the intersection of 204th Street NE on the east side of 67th Avenue NE
  • Continue miscellaneous roadside cleanup and property restoration

Week of November 4

Crews were scheduled to:

  • Begin constructing a block wall on the west side of 67th Avenue NE between the museum and 204th Street NE
  • Begin installing lights and signals on Centennial Trail near the Prairie Creek culvert at 69th Avenue
  • Continue installing the 24-inch sanitary sewer line on the east side of 67th Avenue NE between the museum and 204th Street NE
  • Prepare and pave driveway approaches on the west side of 67th Avenue between the museum and 204th Street NE and near the Prairie Creek culvert at 69th Avenue
  • Complete installation of stormwater drainage system between the museum and the intersection of 204th Street NE on the east side of 67th Avenue NE
  • Continue miscellaneous roadside cleanup and property restoration

Week of October 28

Crews were scheduled to:

  • Begin installing the 24-inch sanitary sewer line on the east side of 67th Avenue NE between the museum and 204th Street NE
  • Prepare and pave driveway approaches on the west side of 67th Avenue between the museum and 204th Street NE and near the Prairie Creek culvert at 69th Avenue
  • Complete installation of stormwater drainage system between the museum and the intersection of 204th Street NE on the east side of 67th Avenue NE
  • Continue miscellaneous roadside cleanup and property restoration

Week of October 21

Crews were scheduled to:

  • Continue demolition of the existing roadway, curbs and sidewalks on the east side of the roadway
  • Resume installing the 8-inch recycled (non-potable) water line between the museum and the intersection of 204th Street NE on the east side of 67th Avenue NE
  • Resume installation of stormwater drainage and infiltration system between the museum and the intersection of 204th Street NE on the east side of 67th Avenue NE
  • Continue miscellaneous roadside cleanup and property restoration

Week of October 14

Crews were scheduled to:

  • Place the first layer of asphalt on the west side of 67th Avenue NE between 204th Street NE and the museum
  • Place concrete sidewalk and driveways on the west side of 67th Avenue NE between 204th Street NE and the museum
  • Shift two-way traffic back to the west on 67th Avenue NE, between the museum and the intersection of 204th Street NE, pending favorable weather and paving progress
  • Continue miscellaneous roadside cleanup and property restoration

Week of October 7

Crews were scheduled to:

  • Begin preparations for placing curb and paving the west side of 67th Avenue NE between 204th Street NE and the museum
  • Complete restoration activities associated with the installation of the Prairie Creek culvert replacement at 69th Avenue near the future Centennial Trail
  • Continue miscellaneous roadside cleanup and property restoration

Week of September 30

Crews were scheduled to:

  • Complete remaining road excavation work on the west side of 67th Avenue NE between 204th Street and the museum
  • Begin preparations for placing curb on the west side of 67th Avenue NE between 204th Street NE and the museum
  • Complete installation of the Prairie Creek culvert replacement at 69th Avenue near the future Centennial Trail, including work on Saturday, September 28. No road closure on 67th Avenue NE is required.
  • Continue miscellaneous roadside cleanup and property restoration

Week of September 23

Crews were scheduled to:

  • Resume installing storm drainage infiltration systems between 211th Place NE and 204th Street NE on the east side of 67th Avenue NE
  • Continue preparation work and begin installation of the Prairie Creek culvert replacement at 69th Avenue near the future Centennial Trail. No road closure on 67th Avenue NE is required.
  • Continue miscellaneous roadside cleanup and property restoration

Week of September 16

Crews were scheduled to:

  • Continue installing the stormwater main and crossings between 211th Place NE and 204th Street NE
  • Begin preparations for Prairie Creek culvert replacement work at 69th Avenue near the future Centennial Trail
  • Shift two-way traffic further to the east on 67th Avenue NE, between the museum and the intersection of 204th Street NE, pending favorable weather
  • Continue miscellaneous roadside cleanup and property restoration

Week of September 9

Crews were scheduled to:

  • Continue installing the stormwater main and crossings between 211th Place NE and 204th Street NE
  • Install 2-inch water services south of Portage Creek
  • Shift two-way traffic to the east on 67th Avenue NE, between the museum and the intersection of 204th Street NE
  • Continue miscellaneous roadside cleanup and property restoration

Week of September 2

Crews were scheduled to:

  • Resume installing the stormwater main and crossings between 211th Place NE and 204th Street NE
  • Install 2-inch water services south of Portage Creek
  • Continue miscellaneous roadside cleanup and property restoration

Please note that crews will not be working September 2 in observance of Labor Day.

Week of August 26

Crews were scheduled to:

  • Resume installing the 8-inch recycled (non-potable) water line between the Pioneer Museum and 211th Place NE on the east side of 67th Avenue NE
  • Continue miscellaneous roadside cleanup and property restoration

Week of August 19

Crews were scheduled to:

  • Continue installing storm drainage infiltration systems between the Pioneer Museum and 211th Place NE on the east side of 67th Avenue NE
  • Resume installing the 8-inch recycled (non-potable) water line between the Pioneer Museum and 211th Place NE on the east side of 67th Avenue NE
  • Continue restoring property behind recently installed sidewalks and driveways

Week of August 12

Crews were scheduled to:

  • Install a new fire hydrant on the west side of 67th Avenue NE, near Portage Creek. A short-term water service disruption was necessary. Affected customers were notified of any utility shutdowns.
  • Continue installing storm drainage infiltration systems between the Pioneer Museum and 211th Place NE on the east side of 67th Avenue NE
  • Begin restoring property behind recently installed sidewalks

Week of August 5

Crews were scheduled to:

  • Complete installation of the Prairie Creek Culvert
  • Remove creek and sewer bypass systems
  • Grade driveway approches for asphalt paving
  • Begin installing storm drainage infiltration systems between the Pioneer Museum and 211th Place NE on the east side of 67th Avenue NE

Week of July 29

Crews were scheduled to:

  • Complete installation of the Prairie Creek Culvert
  • Remove creek and sewer bypass systems
  • Grade driveway approches for asphalt paving
  • Begin installing storm drainage infiltration systems between the Pioneer Museum and 211th Place NE on the east side of 67th Avenue NE

Week of July 22

Crews were scheduled to:

  • Complete installing the Portage Creek culvert under 67th Avenue NE; restore Portage Creek
  • Begin installing storm drainage infiltration systems between the Pioneer Museum and 211th Place NE on the east side of 67th Avenue NE

Week of July 15

Crews were scheduled to:

  • Pre-assemble and begin installing the Portage Creek culvert under 67th Avenue NE; more information on the Home Page
  • Begin installing storm drainage infiltration systems between the Pioneer Museum and 211th Place NE on the east side of 67th Avenue NE

Week of July 8

Crews were scheduled to:

  • Install sidewalks and driveways on west side of 67th Avenue NE
  • Complete a stream bypass for Portage Creek near the future Centennial Trail
  • Construct and install replacement culvert for Portage Creek near the future Centennial Trail
  • Install new water services south of the Pioneer Museum on 67th Avenue NE

Week of July 1

Crews were scheduled to:

  • Begin installation of sidewalks and driveways on west side of 67th Avenue
  • Install silt fencing around the vicinity of Portage Creek near 67th Avenue NE
  • Begin preparations for Portage Creek culvert replacement work

Please note that crews will not be working July 4-5 in observance of Independence Day.

Week of June 24

Crews were scheduled to:

  • Finish roadway grading and begin paving on west side of 67th Avenue NE between the Pioneer Museum and Lebanon Street. This will include a short section of 211th Pl NE, as well.
  • Begin preparations for placement of sidewalks on west side of 67th Avenue NE between the Pioneer Museum and Mission Motors.

Week of June 17

Crews worked two shifts most of the week. Below is a list of what was scheduled for each shift.

Daytime work (7 a.m. - 3:30 p.m.):

  • Continue installation of stormwater drainage system on the west side of 67th Avenue NE north of 211th Place NE
  • Begin testing of recently installed stormwater drainage and water service systems
  • Begin installation of new curbs on 67th Avenue NE south of 211th Place NE
  • Excavate west portion of the 211th Place NE intersection in anticipation of paving

Nighttime work (7 p.m. - 6 a.m., June 17-20):

  • Excavate narrow quarter-mile section of 67th Avenue NE between 211th Place NE and Lebanon Street
  • Install stormwater drainage systems across 67th Avenue NE between 211th Place NE and Lebanon Street

Week of June 10

Crews were scheduled to:

  • Continue installation of electrical conduits for lighting near the future location of the Centennial Trail
  • Continue roadway grading on the west side of 67th Avenue NE north of 211th Place NE
  • Continue installation of stormwater drainage systems on the west side of 67th Avenue NE north of 211th Place NE
  • Begin testing of recently installed stormwater drainage and water service systems

Week of June 3

Crews were scheduled to:

  • Continue installation of reclaimed water main near Twin City Foods
  • Continue installation of electrical conduits for lighting near the future location of the Centennial Trail
  • Begin roadway grading on the west side of 67th Avenue NE north of 211th Place NE
  • Continue installation of stormwater drainage systems on the west side of 67th Avenue NE north of 211th Place NE

Week of May 27

Crews were scheduled to:

  • Continue installation of reclaimed water main near Twin City Foods
  • Continue installing electrical conduit for future 211th Place NE traffic signal
  • Install electrical conduits for lighting near the future location of the Centennial Trail
  • Remove landscaping on west side of 67th Avenue NE north of 211th Place NE

Week of May 20

Crews were scheduled to:

  • Continue installation of stormwater drainage systems on the west side of 67th Avenue NE
  • Begin installation of reclaimed water main near Twin City Foods
  • Rough grade the future Centennial Trail east of 67th Avenue NE
  • Begin roadway grading on the west side of 67th Avenue NE near the Stillaguamish Valley Pioneer Museum in anticipation of placing curb and gutter
  • Install electrical conduit for the future 211th Place NE traffic signal

Week of May 13

Crews were scheduled to:

  • Continue installation of stormwater drainage systems on the west side of 67th Avenue NE
  • Begin installation of reclaimed water line
  • Remove existing vegetation in future location of the Centennial trail
  • Clear and grade roadway on the west side of 67th Avenue NE near the Stillaguamish Valley Pioneer Museum

Week of May 6

Crews were scheduled to:

  • Finalize installation of the new water main along 211th Place NE, and continue installing new water services, fire hydrants and stormwater drainage systems on the west side of 67th Avenue NE

Week of April 29

Crews were scheduled to:

  • Continue installing new water services, fire hydrants and stormwater drainage systems on the west side of 67th Avenue NE and water services on 211th Place NE

Week of April 22

Crews were scheduled to:

  • Install new water services, fire hydrants, and begin construction of a stormwater drainage system on west side of 67th Avenue NE, from Portage Creek north to the 76 Gas Station

Week of April 15

Crews were scheduled to:

  • Restripe the roadway
  • Install erosion control measures, such as silt fences
  • Saw-cut sections of the existing roadway
  • Remove landscaping in the project area

Week of April 8

Crews were scheduled to:

  • Mobilize equipment to the site and delivering materials and supplies to the construction yard on 211th Place NE
  • Stake out the construction and utility siting
  • Place construction signage, such as “Road Construction Ahead” signs